R3C06
Typical set-up for deck erection as seen from the Ting Kau bridge tower. The deck on the trunk of the tower was initially erected by forming a working base with standard struts and girders. Four derrick cranes are lifted by strand-jack to the base for onward extension of the bridge deck on both sides. In order to stabilise the partially completed deck from wind, the deck was temporarily anchored with tie cables.
|