PCT02

PUBLIC HOUSING
With the ground floor completed and the slab of first floor still under temporary support, the steel reinforcement fixing for the first floor wall is almost completed. Timber forms will then be erected after the steel is inspected by an engineer. Note the special formwork used on the in situ reinforced concrete facade on the external wall. The facade for the upper floors is constructed using precast units instead of forming by in situ method