A05

The fabricating yard for the modulated roof frame could accommodate up to 10 modules a time, with a work cycle of about 25 days for each module. The covered structure seen in the back end of the row was a moveable workshop, which could slide to the required location on rail track. Anti-rusting treatment to the steel frame using sand-blasting was completed within the workshop.